Trinity Fellowship is much more than a church building on Hollywood Road. Trinity is all about people – people who have a heart of compassion for reaching others with God’s love and helping them find a place to love and serve others, and to grow in their relationship with Christ. That’s why our message today is, “This is your house.” In saying this, we want to communicate that we are building a house that will be very significant on four levels:

 

The first level is our declaration to God, affirming that this is His house. Psalm 127:1 says, “Unless the Lord builds the house, they labor in vain who build it.” From the very inception of Trinity Fellowship, our intention has always been to hear God’s voice and do what He is telling us to do. Without a doubt, we believe God has told us to build this building and make room for the people He is bringing here.

 

The second level is a message to our congregation. Your sweat and your efforts, your prayers and your finances, have gone into making this church what it is today and what it will be in the future. This is the place you come to worship, to receive ministry and be equipped to lead others, and to fulfill the calling that’s on your life.

 

The third level is the people of our city who are looking for a home, a place to belong and get connected. Statistically, there are 67,000 people in Amarillo with no religious affiliation. Many of those are hurting, needy and disconnected. Our message to them is, you are welcome here. Please come and find comfort, healing and hope, and discover your place in God’s kingdom.

 

The fourth level is a proclamation to Amarillo and the surrounding area that “This Is Your House.” With our new 4,000-seat sanctuary and expansive foyer, we will have the capacity to host large, city-wide events – high school graduations, seminars or conferences – and to use that as a tool to give back to our community. Trinity Fellowship will become a hub of activity as well as a spiritual influence to tens of thousands of people.

 

 

 

Winter 2007-08

  • Stage lifts are dropped into worship center
  • Roof put on worship center; building weatherproofed so interior work can begin
  • Dirt excavated for sloped seating areas around the stage.
  • Interior worship center finishes begin – drywall, painting, ceilings, audio/visual systems

 

Spring 2008

  • Exterior finishing continues
  • Sitework and paving of new parking areas; curb & gutter, landscaping, sprinkler systems
  • Interior finishes continue

 

Summer 2008

  • Audio/Visual systems completed
  • Commissioning of the stage lifts
  • Furnishings installed
  • Building inspected and approved

 

Fall/Winter 2008

Move-in celebration

March 2008

 

Sanctuary

  • Structural steel is 95% complete.
  • Elevated seating area is 60% complete.
  • All tilt-up panels are in place.
  • Roughin of all the mechanical , plumbing, and electrical systems continue.
  • Metal framing 75% complete
  • Roof system is complete

 

Children’s area

  • Interior metal studs have been completed on the upper and lower leves.
  • Sheetrock work is complete.
  • Tape, texture is complete and painting is started on the lower level.
  • Electrical, plumbing, fire sprinkler systems, and heating & air conditioning rough-in work is complete.
  • Exterior finishes have begun – Efis synthetic stucco, the central plant building is completed, and the North entrances and East exterior walls will be finished next.
  • South side exterior is being prepped for painting.
  • The playground interior finishes, walls and ceiling are complete.

 

Youth Commons

  • Metal stud framing is 75% complete.
  • Roughin of all the mechanical, plumbing, and electrical systems is 60% complete.
  • Roof system is completed.